← All companies

Operates zero-carbon-anchored data center campuses for AI and HPC, describing itself as an energy operator first and a data center operator second.

TeraWulf's core asset is controlled power: roughly 2.3 GW under control across five named campuses — Lake Mariner in western New York, plus Justified, Muskie, Lake Hawkeye and Chesapeake. Lake Mariner sits on a retired coal plant site, which is the whole strategy in miniature: the retired plant's energized interconnection is the scarce asset, not the shell or the GPUs. The company converted from bitcoin mining into long-term AI/HPC hosting leases and now describes itself as an energy infrastructure company first. Its own framing — "architected for a power-constrained future" — is the clearest statement of why this category belongs in an energy directory at all.

Headquarters
Easton, MD
Employees
51–200
Business model
Asset owner
Ownership
Public
Founded
2021
Listing / owner
Nasdaq: WULF
Products
Lake Mariner (NY)JustifiedMuskieLake HawkeyeChesapeake
Sells to
AI companiesHyperscalersCloud providers

Interconnection queue footprint

as of 2026-03-20
250 MW
Total capacity
1
Projects
0 · 0 MW
Active
0 · 0 MW
Operational
0
Withdrawn
250 MW
Avg project size
1
States
2025
First queued
Technology mix (by capacity)
Other1 · 250 MW · 100%
Markets
NYISO 1
Where the projects are
AKMEVTNHWAIDMTNDMNILWIMINYRIMAORNVWYSDIAINOHPANJCTCAUTCONEMOKYWVVAMDDEAZNMKSARTNNCSCDCOKLAMSALGAHITXFL
1 state
Largest project
Wulf Compute Data Center II
250 MW · Other · NY · NYISO · System Impact Study
Sources
  • · Curated research

Written profiles are hand-entered and not independently verified. Queue figures are computed from ISO interconnection data and reflect requested capacity, not built capacity.

More in Data centers